Hydro power plant Zeleni Jadar
The bottleneck capacity of the Zeleni Jadar power plant is 249 kilowatts (kW). The power plant is connected to the local 10 KV medium-voltage grid of the Bosnian electricity supplier Elektro Privreda.
Installed technology
The heart of the Zeleni Jadar small hydropower plant is a Kaplan turbine with a bottleneck capacity of 249 kW.
Location
Country: Bosnia and Herzegovina
Region: Vlasenica
Nearest town: Bratunac
Connected to local Elektro Privreda electricity grid
GPS coordinates Zeleni Jadar: 44°04’35.5″N 19°15’39.2″E
Technology
Kaplan Turbine
Bottleneck capacity
249 kW
EPC contractor
Green Energy-R
Commissioning
January 2020